Economic Development
Click to Home

Go To Search
Section Links
HomeMailRSS
Print
Current Projects
The City of Seabrook strives to build a city that is cohesive and strategically designed to provide the best quality of life to Seabrook residents and visitors. Plans and projects work together to provide road maps for city staff in developing a city that works for its people. Some plans are geographically specific, while others include the whole city, while even others are focused on a specific component of city development. 



CITY PLANS
City plans vary by department, for example some are geographically specific, while others include the whole city, and then there are those that are focused on a specific component of city development. Click the links below to learn more about each plan!




CURRENT PROJECTS
Listed below are current city projects many that may effect transit within the city. For more information about city projects please email .  

SH 146 Expansion Project
After many years of doubt, the expansion of State Highway 146 will soon become a reality. The expansion of the highway is greatly needed to alleviate daily traffic congestion and will also allow safe passage for motorists during hurricane evacuations. SH 146 is an official hurricane evacuation corridor. Learn More...

Water Plant Relocation 
The Seabrook Water Plant Relocation project is underway. It was awarded on September 20, 2016 for total bid amount of $1,922,307.80 to Long and Son, Inc. The project involves the demolition of the existing 600,000 gallon ground storage tank located on Humble Dr. and the construction of 1,000,000 gallon ground storage tank located off of Lakeside Dr. Project is expected to be compete mid August, 2017.

  • Drainage and Waterline Piping – In progress
  • Exterior piping, fitting and valve installation – In progress
  • Internal sandblast and paint portion complete
  • Pump building foundation complete; CMU walls to start week of 5/22/17.
  • Pump pads poured 4/21/17, 2 pumps set.
  • Exterior shroud installed for tank wall primer and coating; exterior being painted.

Public Works & Animal Shelter Complex

  • Permanent power 5/15/17
  • Admin building final paint in progress
  • Admin building electrical and plumbing trim out in progress
  • Operations A final paint, electrical and plumbing trim out in progress
  • Operations B final paint, electrical and plumbing trim out in progress
  • Irrigation installation complete
  • Landscaping installation complete
  • A/c startups began 5/24
  • Furniture delivered 5/30. Final install to be set at a later date.
  • Scheduled substantial completion June 2017

Todville Sanitary Sewer Line Replacement Project
Seabrook Public Works will be making sanitary sewer improvements along Todville Rd. from Brummerhop St. to East Meyer St. Design is underway for this project which involves the replacement/rehabilitation of approximately 6,055 feet of 8 and 10 inch sewer mains using pipe burst and open cut construction methods. The construction will also include the replacement/rehabilitation of manholes, replacing sewer crossings and reconnecting existing sewer services.

Cedarbrook Court Street Improvements 

Cedarbrook Court, located just off North Meyer in front of the baseball fields will receive a much needed improvement this summer. This project is the second phase to replace the concrete pavement in Baybrook Sec. 1. Current estimate of construction cost is $211,482.49. Bid opening was May 11, bid awarded to RAC Industries, LLC. For $159,819.00.


Improvements will include replacing the existing old concrete pavement with new 6-inch concrete pavement and 6-inch concrete curbs. Adjacent driveways along the street replacement will be removed and be replaced with 6-inch concrete
 up to the existing right-of-way. This street improvement is part of an ongoing project funded in part by the Sanitation Franchise Fee transfer for Street Repair and Improvements. Construction is anticipated to start mid June, 2017. 

Lake Mija Village – Subdivision

  • Scheduled to finish lift station installation
  • Installed power poles week of 03/27/17
  • Seabrook Water Department installed water meter to serve lift station week of 4/3/17.
  • AT&T to be onsite TV-ing and repairing sewer service leads.
  • Performed walk-through inspection May 11, 2017 and created a punch list
  • Performed Lift Station startup 5/25

Hester Gully Drainage Improvements
City Council awarded the bid to low bidder GCP Contractors, LLC in the amount not to exceed $123,131.50 at the March 7th council meeting.

Construction started April 24, 2017.

Red Bluff Road Expansion
TxDOT and Harris County is planing a Red Bluff Expansion from Kirby Boulevard to State Highway 146. The purposed of the proposed project is to improve safety and enhance mobility to accomodate existing and expected future growth.  

The proposed improvements include:

  • Constructing two eastbound lanes
  • Converting the existing roadway to a one-way westbound operation
  • Re-stripe the traffic to westbound only on the existing bridge over Taylor Lake
  • Adding a new bridge parallel to the existing bridge for eastbound traffic

The total project length is 1.5 miles of roadway. The project requires 0.3 additional acre of right of way; however, no displacement to local residents is expected.

The environmental review, consultation and other actions required by applicable federal environmental laws for this project are being, or have been carried out by TxDOT pursuant to 23 U.S.C 327 and a Memorandum of Understanding dated Dec. 16, 2014, and executed by the Federal Highway Administration and TxDOT. Learn more... 

Pine Gully Waste Water Treatment Plant
Project is the first phase to relocate the waste water treatment plant and will provide 0.25 MGD capacity. TCEQ TPDES discharge permit application is being developed.

Plans are currently in the design phase.


Community Development
1700 First St.
Seabrook, TX 77586

Ph: (281) 291.5669
Fx: (281) 291.5690

Director
Sean Landis

Building Official
Nick Kondejewski

Building Inspector
Matthew Littleton

Code Enforcement
Alana Rohlfs

Planning
Alesia Hammock

Permitting
Vivian Ramos



News
Hurricane Harvey Relief Drawing
Seabrook Association to give $5,000 to Seabrook families directly impacted by Hurricane Harvey. Read on...
City offices closed for holiday
The City of Seabrook will observe the Thanksgiving holiday on Thursday, November 23 and Friday, November 24, 2017. In observance of this holiday, City of Seabrook offices will be closed. Read on...
View All
Connect with Us
FacebookTwitterYouTube